The ministry of defence
(MoD) on Wednesday (April 4, 2019) added another Act to its own version of
“Comedy of Errors” when it comes to submarine procurement for the navy.
PTI reported on April 4th,
that in a ‘major move’ the MoD started the process to
acquire six advanced diesel-electric submarines under the ambitious “strategic
partnership” (SP) model at a cost of around Rs 45,000 crore.
The submarines, fitted
with anti-ship cruise missiles (preferably Brahmos) and other lethal weapons,
will be constructed in India jointly by an Indian defence major and a foreign
submarine manufacturer under the Project-75(I) programme.
Sadly, this major move
has been taking place since 2008 and the project’s progress can now be
calculated by the same principal of the famous mathematical problem of a monkey
climbing a greased pole where he jumps up three feet only to slip down two.
Sources, PTI reported,
said the Expression of Interest (EoI) will be issued to leading manufacturers
of advanced submarines in four weeks. The defence ministry, the
report said, has started the process for selecting both the Indian and foreign
defence entities for the Rs 45,000-crore project.
Most do not know what to
make of this. Does this mean the project is finally gathering steam or will it
just lapse like it has done so many times in the past? So much so, that most
believe that the project has become like the famous Schrödinger's cat — it’s at
the same time both alive and dead.
From 2008 to 2019, the
Indian public has been forced to bear witness to a farcical theatre of the
absurd by the GoI, MoD, defence acquisition council (DAC) and cabinet committee
for security (CCS).
In case of Project 75
(I), the initial Request for Information (RFI) was already issued in 2008 to
Armaris, HDW and Rosoboronexport for six submarines with air-independent
propulsion (AIP) and land-attack capability.
The project was
re-planned in 2010 and after DAC’s approval, RFI was re-issued in September
2010. The RFI lapsed multiple times till 2013 when the renewed RFI was rejected
by CCS.
In 2014, CCS in all its
brilliance decided to build all the submarines in India. Along with the
state-owned Mazagon Dock, Hindustan Shipyard, and Cochin Shipyard,
privately-owned shipyards like Larsen & Toubro and Pipavav Shipyard were
now allowed to bid for the project in collaboration with a foreign shipyard.
In June 2017, it was
reported that the BJP government had now decided on a contract for construction
that would be awarded under “Strategic Partnership" policy, which would
eliminate state-owned shipyards from contention. However, this approval too
lapsed in February 2018. In January this year DAC renewed the approval and now the
MoD is slated to issue an EoI in four weeks’ time.
No wonder nobody in
defence circles is keeping their fingers crossed this time. By our usual
standards, even if by mistake the government signs the transfer-of-technology ToT deal, which is
highly doubtful given the polls are around the corner, the project is bound to
falter.
If NDA wins the
election, MoD will have to deal with a new minister, who will need to
reacquaint himself or herself with the ministry. This takes time and the
approval will, again, lapse. If UPA wins, then there will be a complete change
in Cabinet and the acquisition will be reviewed by the new councils and the
approval will surely lapse again. So, it is highly doubtful that this project
will see light of the day anytime soon.
Sadly, the history of
submarine projects in India has always been one of delays, apathy and adoption
of a procedure that embodies utter lack of common sense.
Project 75, Project
75(I)’s predecessor, for instance, was born on 1997 under which the Indian
government planned to buy 24 diesel-electric submarines and by 1998 India had
begun negotiations with Direction des Constructions Navales (DCN) —a French
industrial group known for naval defence, known simply as Naval Group post 2017
— for four Scorpène-class submarines of which two was to be built in Mazagon
Docks Limited from knocked-down kits.
Till this time, there
were two schools of thought that vied for importance in the Indian Naval
decision-making circles. The most prominent was the one that backed investing
in aircraft carriers, which, they said, would be the future of naval warfare
enabling the navy operating it unmatched force projection capabilities in any
given region. The other school of thought maintained that aircraft carriers
were nothing but big targets that can be picked off easily by stealthy
submarines and that future wars would see an unprecedented use of any navy’s
underwater arm.
Navy thinkers, however,
were convinced by the first school of thought and wanted to buy the Kiev-class
aircraft carrier Admiral Gorshkov that the Soviet Navy had inducted in 1987 and
decommissioned in 1996. After years of negotiations, the deal was finally inked
in January 20, 2004. The aircraft carrier was finally inducted into service,
after extensive repair and refurbishment, on November 16, 2013 as INS
Vikramaditya.
![]() |
| INS Vikramaditya |
However, after the
Kargil war in 1999, Indian planners had nonetheless “realised” the importance
of an underwater arm and had approved of a 30-year submarine building plan that
involved two parallel production lines Project 75 and Project 75(I).
It would take India
another six years to sign a series of transfer-of-technology (ToT) contracts to
build six submarines in Mazagon Docks Limited with Armaris — a joint company
set up in 2002 by DCN and THALES.
DCN was then designated
as the prime contractor in partnership with Navantia — a Spanish state-owned
shipbuilding company.
Steel cutting for the
first submarine of the project would begin only a year later, on December 14,
2006 and hull construction was started on May 23, 2007. The project was plagued
by one delay after another and by 2014, it was running four years behind
schedule.
The first submarine INS
Kalvari was finally launched in October 28, 2015 and sea trials began on May 1,
2016.
![]() |
| INS Kalvari |
However, it was time for
the next fiasco as the Black Shark torpedoes, from WASS, that were supposed to
arm these submarines was cancelled due to corruption allegations against its
sister company AgustaWestland.
For now, these
state-of-the-art submarines will have to do with ancient and obsolete Surface
and Underwater Target (SUT) torpedoes.
![]() |
| INS Chakra II |
It is common knowledge
that the submarine arm of the Indian Navy is now very weak.
Navy now has only one
Arihant-class SSBN, one Akula-II class SSN (leased from Russia), and 14 SSKs
which includes nine Sindhughosh-class (or Russian Kilo-class) submarines from
the eighties, four Sishumar class (or German Type 209) submarines also from the
eighties and a lone Kalvari class (Scorpène-class) submarine.
India lost a
newly-refurbished Sindhughosh-class submarine INS Sindhurakshak on August 14,
2013.
![]() |
| INS Sindhughosh |
| A Shishumar-class submarine |
With no progress in
Project 75(I) in view, what any sane-minded MoD would have done is gone for three
more AIP-enabled Scorpène-class submarines from Mazagon Docks Limited which by
now has mastered the process of building the submarines. The dock authorities
in 2017 had said that it would be able to churn out the next batch of
submarines within three to four years of getting the green signal.
The next logical step is going for a
govt-to-govt deal with the French for their nuclear-powered Barracuda class
SSNs. Or at least an Australia type deal for Shortfin Barracuda Block 1A —
which is a diesel-electric version of the SSN design.
Going by Indian Navy’s
future blue-water ambitions, it needs at least 12 SSNs and 8 SSBNs and 22 SSKs
and at least three aircraft carriers.
India
is already building four 6000-tonne Arihant-class SSBNs with design help from
Russia. INS Arihant is already operational, INS Arighat is undergoing sea
trials and is expected to be commissioned late in 2019 or in early 2020. The
other two will follow before 2025. After that India will embark on building
four 12,000-tonne SSBNs for which nuclear reactors are already being
fabricated.
![]() |
| INS Arihant |
Also
in the works are a batch of six SSNs that India is building with major design
inputs from Russia. These will be starting to go into sea trials sometime in or
after 2030. But India need SSNs now and leasing one from Russia will not work
in the future as India's assets in the water, which will need protection, will
grow by then. The Navy would need at least four SSNs to protect two of its
aircraft carriers and two SSBNs which would be in service.
Why Indian Navy is so
hung up on Project 75(I) is its vertical launch capability of Brahmos cruise
missiles. These subs, with their extended-range Brahmos would be a deadly force
to reckon with in the sub-continent, Indian Ocean and off course in South China
Sea where these will be able to threaten Chinese aircraft carriers from
stand-off ranges if the can be built on time. But as to when we can expect this
project to finally bear fruit is hard to tell and all we as Indian Navy’s
well-wishers can do is follow
Alexander
Dumas’ advice in the concluding line of his adventure novel "The Count of
Monte Cristo" – “Wait and hope”.
Note:
SSN - nuclear-powered general-purpose
attack submarine
SSBN - nuclear-powered ballistic missile
submarines
SSK - diesel-electric
submarine
AIP - Air Independent
Propulsion System